Consolidating the Computing Foundation, Ensuring Secure Operation|ZDATA's Mingwei 110kV No.2 Substation in Zhangjiakou and Ulanqab 110kV Yaxin Yunlian Substation Officially Commence Operation
Recently, the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation have successively completed power transmission. During project construction, the design principles of high reliability, green energy efficiency, adaptability, and intelligent integration were strictly adhered to, providing reliable assurance for stable power supply.
Dual Hubs Successively Commence Operation, Computing Base Upgraded
► The Mingwei 110kV No.2 Substation commenced construction in early October 2024. During construction, ZDATA organized construction teams to overcome external challenges such as right-of-way acquisition delays and winter construction constraints. It achieved dual-circuit power transmission ahead of schedule on June 25, 2025, providing robust support for the power supply of ZDATA's Yu County project cluster.

► The Ulanqab 110kV Yaxin Yunlian Substation, located in the heart of the Chahar High-Tech Zone, faced complex land acquisition and construction bottlenecks. The project team proactively collaborated with relevant departments of Ulanqab Power Supply Company to overcome grid access restrictions during critical security periods for the national college entrance exams. By establishing a "night construction window" and "green approval channel," they completed the full line connection on schedule. The entire line passed acceptance on June 30, ensuring the substation achieved its power transmission target on July 1.

Racing Against Time, Experiencing ZDATA's "Acceleration"
► The successive commissioning of the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation will provide stable, high-capacity power support for the massive regional data center clusters. This will underpin their massive data computing and storage tasks, facilitate interconnectivity in regions like Beijing-Tianjin-Hebei and Ulanqab, and deliver solid energy support for regional digital economic development.

Recommended News
-
03/132026
International Recognition, Advancing with Honor | ZDATA's Malaysia GP3 Project Awarded GreenRE Platinum Certification
Recently, ZDATA's GP3 hyperscale data center project in Johor, Malaysia, has been awarded the GreenRE Platinum Certification. -
06/272022
ZDATA achieves "ITSS Operation and Maintenance Service Capability Maturity Level 3" certification.
In June 2022, the Information Technology Service Branch of the China Electronic Industry Standardization Technology Association organized the "Information Technology Service Operation and Maintenance Capability Maturity" compliance assessment expert review meeting. ZDATA, based on the maturity model standards, implemented the management of system operation and maintenance service capabilities, established comprehensive management systems for personnel, processes, technology, and resources, and effectively implemented them. After multiple rounds of reviews, leveraging the profound practical experience and technological expertise accumulated in the data center ITO operation and maintenance services, ZDATA successfully obtained the ITSS operation and maintenance service capability maturity level three certificate.